Mango Peeler production Essay Help.

Answer: Mango Peeler production

Mango Peeler production

The bill of materials for the mango peeler would describe the list of raw materials that would be required to make the finished product. The company provides an illustration of the concept of specification in the provisions of the figure provided below (Nobil, 2018).

Figure 1: Component structure for the mango peeling bladeMango Peeler production

 

Table 1: Product definition before defining Bills of Materials

Image Code Product Reference Description
MP10 CUT10 Mango peeler 10 cm
BLM BLA Cutting blade
HAN1 HAN Grip handle
HAN2 SUP Grip support
CLT CLT Plastic Cleat

 

The firm has a further production for the packaging material of the mango peeler. The peeler is basic in natures. The package is cuboid and made up of six recyclable parts which simply clip on to each other to form a stable structure (Kazemi,2018). Mango Peeler production

Table 2: Product definition for the packaging material

Image Code Product Reference Description
SDP010 LN Long side panel 10 cm, 4 pieces
TB002 SH Top and bottom panels 2 cm, 2 pieces

 

Bill of materials

For the assembly of the product, the firm provides a description of the bill of materials for intermediate products and that of its final assembly, Mango Peeler production

Table 3: Bill of materials for the peeler

Product reference Quantity Unit of measure
BLA 1 Pieces
HAN 1 Pieces
SUP 1 Pieces
CLT 1 Pieces

 

Table 4: Bill of materials for the packaging

LN 10 cm
SH 2 cm

 

Table 5: Total quantities per mango peeler

Product reference Quantity Unit of measure
BLA 1 Pieces
HAN 1 Pieces
SUP 1 Pieces
CLT 1 Pieces
LN 40 (4 * 10) cm
SH 4 (2 * 2) cm

 

Master schedule of production

Table 6: Master Production Schedule for demand of mango peeler

Demand Management Week 1 Week 2 Week 3 Week 4
Weekly demand for the mango peeler 500 500 500 500
Working days in a week 6 6 6 6
MPS daily demand for the mango peeler 83 83 83 83

 

Production schedule

Table 7: Production schedule

Demand management Week 1 Week 2 Week 3 Week 4 Week 5 Week 6
Demand 500 500 500 500 500 500
Production 0 1000 500 500 500 500
Delivery of raw materials 0 2500 0 0 2500 0
Raw materials 0 1500 1000 500 2500 2000

 

Since it takes the suppliers one week from time of placing an order to delivery of the raw materials, the firm will have to contend with one week of not satisfying market demand in the initial month of production. With the raw materials arriving in week two, the firm can successfully fulfill demand for the first and second week during the second week. To avoid of a repeat of the same situation in the second month, the firm needs to place its order in the fourth week of the first month (Mokhtari,2018). Mango Peeler production

 

References

1.     Nobil, A. H., Sedigh, A. H. A., & Cárdenas-Barrón, L. E. (2018). A Generalized Economic Order Quantity Inventory Model with Shortage: Case Study of a Poultry Farmer. Arabian Journal for Science and Engineering, 1-11.

2.     Kazemi, N., Abdul-Rashid, S. H., Ghazilla, R. A. R., Shekarian, E., & Zanoni, S. (2018). Economic order quantity models for items with imperfect quality and emission considerations. International Journal of Systems Science: Operations & Logistics5(2), 99-115.

3.     Mokhtari, H. (2018). Economic order quantity for joint complementary and substitutable items. Mathematics and Computers in Simulation154, 34-47.

 

 

Question: Mango Peeler production

your company has developed a simple, but amazingly effective mango peeler. it is constructed from a blade and a supergrip handle that has a top piece and a bottom piece. the assembled mango peeler is packed in a simple recycled card pack. all the parts simply clip together and are bought in from suppliers, who can deliver the parts within one week of orders being placed. given enough parts, your company can produce products within a day of firm orders being placed. initial forecasts indicate that demand will be around 500 items per week. (a) draw a component structure and bill of materials for the mango peeler. (b) develop a master production schedule for the product. (c) develop a schedule indicating when and how many of each component should be ordered (your scheduler tells you that the economic order quantity, eoQ, for all parts is 2,500). Mango Peeler production